Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
39W63 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 764/।।।(2)/08-85 (प्रा0आ0)/07 दि. 24.03.08
TS Amount (lakhs) : 107.7 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
110.25
Resanction Cost :
110.25
Tentative Cost :
110.25
Exp. Upto Last Fy : 102.30
For CFY 2024-2025
Remaining : 7.95
Demand : 7.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 102.30
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
16 years 3 months ago
24 Mar 2008
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
भारत सरकार के पत्र संख्या 8बी/यूसीपी/06/91/2012/एफसी/2714 दिनांक 31.03.2016 द्वारा आॅफ लाइन (Offline) विधिवत स्वीकृति प्राप्त।
3.00 किमी0 में पहाड कटान कार्य पूर्ण। दायित्व शेष।
-- as on 26-Dec-2023
Physical Peramenters