Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
39W67 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 2488(1)/111 (2)/08 -03 (मु0मं0घो0)/08 दि. 25.07.08
TS Amount (lakhs) : 110.25 Lacs
Financial Detail
Sanction Cost : 110.25 Lacs
Resanction Cost : 110.25 Lacs
Exp. Upto Last Fy : 100.82 Lacs
For CFY 2024-2025
Remaining : 9.43 Lacs
Demand : 9.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 100.82 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
15 years 9 months ago
25 Jul 2008
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
नापभूमि में मार्ग निर्माण किया गया, जिस हेतु आॅन लाइन पत्रावली का निरस्त किया गया है।
3.00 किमी0 में पहाड कटान & पार्ट-।। का कार्य पूर्ण। दायित्व शेष
-- as on 26-Dec-2023
Physical Peramenters