Work Profile Report [39W672]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : fजलाfधकारी का पत्र संख्या 45/fजला योजना /अर्थ एवं संख्या/लो0fन0fव0/2018-19 fदनांक 28.11.2018
TS Amount (lakhs) : 10 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
10.00
Resanction Cost :
10.00
Tentative Cost :
10.00
Exp. Upto Last Fy :
7.97
For CFY 2024-2025
Remaining :
2.03
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
7.97
Construction Started
Sanction on : 5 years 11 months ago
28 Nov 2018
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
80 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड कटान कार्य पूर्ण। दीवार निर्माण कार्य प्रगति पर है। -- as on 29-Sep-2021
Assets :
Work not linked with IM
Bridges on The Basis of AI: