Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
39W672 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी का पत्र संख्या 45/fजला योजना /अर्थ एवं संख्या/लो0fन0fव0/2018-19 fदनांक 28.11.2018
TS Amount (lakhs) : 10 Lacs
Financial Detail
Sanction Cost : 10.00 Lacs
Resanction Cost : 10.00 Lacs
Exp. Upto Last Fy : 7.97 Lacs
For CFY 2024-2025
Remaining : 2.03 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 7.97 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
5 years 5 months ago
28 Nov 2018
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान कार्य पूर्ण। दीवार निर्माण कार्य प्रगति पर है। -- as on 29-Sep-2021
Physical Peramenters