Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
39W699 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 1326/।।।(2)/19-08 (एमएलए)/2017टीसी ।।। दिनांक 10.03.2019
TS Amount (lakhs) : 91.58 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
91.58
Resanction Cost :
91.58
Tentative Cost :
91.58
Exp. Upto Last Fy : 84.81
For CFY 2024-2025
Remaining : 6.77
Demand : 6.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 84.81
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
10 Mar 2019
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.00 किमी0 में पहाड कटान व दीवार निर्माण कार्य पूर्ण। दायित्व शेष। -- as on 21-Nov-2023
Physical Peramenters