Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 1.500 | 1.5 | 0.000 | 0.000 |
39W70 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 4199/111-2/08 (मु0मं0घो0/08 दिनांक 24.12.08
TS Amount (lakhs) : 110.25 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
110.25
Resanction Cost :
110.25
Tentative Cost :
110.25
Exp. Upto Last Fy : 56.50
For CFY 2024-2025
Remaining : 53.75
Demand : 30.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 56.50
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
15 years 6 months ago
24 Dec 2008
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: Alignment Dispute
1.50 किमी0 में पहाड कटान व दीवार निर्माण कार्य पूर्ण। इससे आगे के भाग में ग्रामीणों द्वारा विवाद किये जाने के कारण मोटर मार्ग का निर्माण नहीं किया गया। -- as on 29-Feb-2024
Physical Peramenters