Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.000 | 0.5 | 0.320 | 0.000 |
39W700 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी का पत्र संख्या 334/विविध/2018-19 दिनांक 25.01.2019
TS Amount (lakhs) : 6.3 Lacs
Financial Detail
Sanction Cost : 6.30 Lacs
Resanction Cost : 6.30 Lacs
Exp. Upto Last Fy : 2.54 Lacs
For CFY 2024-2025
Remaining : 3.76 Lacs
Demand : 3.76 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.54 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
5 years 3 months ago
25 Jan 2019
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
320 मीटर में ही पहाड कटान कार्य पूर्ण -- as on 25-Apr-2024