Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
39W735 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 1490/।।।(2)/20-08 (एम.एल.ए.) /2017टीसी दिनांक 14.08.2020
TS Amount (lakhs) : 4.46 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
20.85
Resanction Cost :
20.85
Tentative Cost :
20.85
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 20.75
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 1 %
Sanction on :
3 years 11 months ago
14 Aug 2020
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
सर्वे कार्य में ग्रामीणों का विवाद है। -- as on 31-Dec-2022
Physical Peramenters