Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4.5 | 4.500 | 0 | 0.000 | 0.000 |
39W776 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 1569(1)/।।।(2)/19-08 (एम.एल.ए.)/2017टीसी-।।। दिनांक 15.06.2021
TS Amount (lakhs) : 331.78 Lacs
Financial Detail
Sanction Cost : 331.78 Lacs
Resanction Cost : 331.78 Lacs
Exp. Upto Last Fy : 304.27 Lacs
For CFY 2024-2025
Remaining : 27.51 Lacs
Demand : 27.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 304.27 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
15 Jun 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
डामरीकरण का कार्य है वनभूमि नहीं पड़ती है। वर्तमान में कार्य पूर्ण । -- as on 26-Dec-2023
Physical Peramenters