Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.2 | 2.2 | 0.000 | 2.2 | 0.000 | 0.000 |
39W802 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 3573(1)/।।।(2)/21-08(एम.एल.ए.)/2017 टी.सी.-।। दिनांक 10.09.2021
TS Amount (lakhs) : 49.81 Lacs
Financial Detail
Sanction Cost : 49.81 Lacs
Resanction Cost : 49.81 Lacs
Exp. Upto Last Fy : 43.78 Lacs
For CFY 2024-2025
Remaining : 6.03 Lacs
Demand : 6.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 43.78 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
2 years 8 months ago
10 Sep 2021
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.20 किमी0 में पहाड कटान कार्य पूर्ण। दायित्व शेष। -- as on 21-Nov-2023
Physical Peramenters