Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
39W807 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 4995(1)/।।।(2)/21-08 (एम.एल.ए.) /2017 दिनांक 22.10.2021
TS Amount (lakhs) : 187.54 Lacs
Financial Detail
Sanction Cost : 187.54 Lacs
Resanction Cost : 187.54 Lacs
Exp. Upto Last Fy : 181.73 Lacs
For CFY 2024-2025
Remaining : 5.81 Lacs
Demand : 5.82 Lacs
Allotment : 5.82 Lacs
Exp in CFY : 0.17 Lacs
Total Up to Date Exp : 181.90 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
22 Oct 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.00 किमी0 में पी.सी. द्वारा डामीरकरण कार्य पूर्ण।
पीसीआर गठित की जा रही है।
-- as on 30-Apr-2024
Physical Peramenters