Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
39W807 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 4995(1)/।।।(2)/21-08 (एम.एल.ए.) /2017 दिनांक 22.10.2021
TS Amount (lakhs) : 187.54 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
187.54
Resanction Cost :
187.54
Tentative Cost :
187.54
Exp. Upto Last Fy : 181.73
For CFY 2024-2025
Remaining : 5.81
Demand : 5.82
Allotment : 5.82
Exp in CFY : 0.51
Total Up to Date Exp : 182.24
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 8 months ago
22 Oct 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
1 year 1 month ago
31 May 2023
Remark
Bottelneck: no issue
3.00 किमी0 में पी.सी. द्वारा डामीरकरण कार्य पूर्ण।
पीसीआर इस कार्यालय के पत्र संख्या 1273/1सी दिनांक 16.05.2024 द्वारा अधीक्षण अभियन्ता को तथा अधीक्षण अभियन्ता का पत्र संख्या 2172/69याता-7/2024 दिनांक 31.05.2024 द्वारा मुख्य अभियन्ता को प्रेषित।
-- as on 12-Jun-2024
Physical Peramenters