Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.75 | 1.75 | 0.000 | 1.75 | 0.000 | 0.000 |
39W808 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 5365(1)/।।।(2)/21-50(प्रा0आ0)/2017 दिनांक 09.11.2021
TS Amount (lakhs) : 46.61 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
46.61
Resanction Cost :
46.61
Tentative Cost :
46.61
Exp. Upto Last Fy : 29.55
For CFY 2024-2025
Remaining : 17.06
Demand : 17.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 29.55
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
2 years 8 months ago
09 Nov 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.75 Km पहाड कटान का कार्य पूर्ण। डिफैक्ट कटिंग व ग्रेड सुधार का कार्य प्रगति पर है। -- as on 21-Nov-2023
Physical Peramenters