Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
39W810 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 6019(1)/।।।(2)/21-08 (एम.एल.ए.) /2017 दिनांक 14.12.2021
TS Amount (lakhs) : 145.72 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
145.72
Resanction Cost :
145.72
Tentative Cost :
145.72
Exp. Upto Last Fy : 108.70
For CFY 2024-2025
Remaining : 37.02
Demand : 22.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 108.70
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
14 Dec 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5.00 किमी0 में पहाड कटान कार्य पूर्ण। कार्य पूर्ण। दायित्व शेष। -- as on 21-Nov-2023
Physical Peramenters