Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
39W821 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 10(1)/।।।(2)/21-08(एमएलए)/2017 टीसी-चार दिनांक 03.01.2022
TS Amount (lakhs) : 4.46 Lacs
Financial Detail
Sanction Cost : 23.43 Lacs
Resanction Cost : 23.43 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 23.43 Lacs
Demand : 0.25 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 4 months ago
03 Jan 2022
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
सर्वे कार्य पूर्ण। ग्रामीणों की अनापत्ति अपेक्षित है। -- as on 31-Jan-2023
Physical Peramenters