Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.3 | 1.3 | 0.000 | 1.3 | 0.000 | 0.000 |
39W825 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 10(1)/।।।(2)/21-08(एमएलए)/2017 टीसी-चार दिनांक 03.01.2022
TS Amount (lakhs) : 0.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
10.71
Resanction Cost :
10.71
Tentative Cost :
10.71
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 10.71
Demand : 0.25
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 6 months ago
03 Jan 2022
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सवे कार्य पूर्ण। ग्रामीणों की अनापत्ति अप्राप्त है। -- as on 30-Aug-2023
Physical Peramenters