Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 0.000 | 0.000 |
39W829 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 498(1)/।।।(2)/22-08(एमएलए)/2017 टीसी दिनांक 07.01.2022
TS Amount (lakhs) : 29.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
29.41
Resanction Cost :
29.41
Tentative Cost :
29.41
Exp. Upto Last Fy : 18.21
For CFY 2024-2025
Remaining : 11.20
Demand : 11.00
Allotment : 2.01
Exp in CFY : 2.01
Total Up to Date Exp : 20.22
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.00 िकमी0 में पहाड कटान कार्य पूर्ण। -- as on 31-Mar-2024
Physical Peramenters