Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.7 | 0.7 | 0.700 | 0 | 0.000 | 0.000 |
39W867 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी रूद्रप्रयाग का पत्र संख्या 508/जिला योजना-03/2022 दिनांक 09.09.2022
TS Amount (lakhs) : 10 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
10.00
Resanction Cost :
10.00
Tentative Cost :
10.00
Exp. Upto Last Fy : 5.85
For CFY 2024-2025
Remaining : 4.15
Demand : 4.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 5.85
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 10 months ago
09 Sep 2022
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 31-Oct-2023
Physical Peramenters