Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 0.000 | 0.000 |
39W885 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. ।/95259/2023 ई-फाईल सं0 31356 /लोक निर्माण अनुभाग-2 दिनांक 01.02.2023
TS Amount (lakhs) : 35.96 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
35.96
Resanction Cost :
35.96
Tentative Cost :
35.96
Exp. Upto Last Fy : 10.01
For CFY 2024-2025
Remaining : 25.95
Demand : 25.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 10.01
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
1 year 5 months ago
01 Feb 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.50 किमी0 में पहाड कटान कार्य पूर्ण। -- as on 31-Mar-2024
Physical Peramenters