Work Profile Report [39W895]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. ।/108219/2023 ई-फाईल सं0 50405 /लोक निर्माण अनुभाग-2 दिनांक 21.03.2023
TS Amount (lakhs) : 3.82 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
7.50
Resanction Cost :
7.50
Tentative Cost :
7.50
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
7.40
Demand :
0.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Alignment Approved
Sanction on : 1 year 9 months ago
21 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
संरेखण आख्या वृत्तीय कार्यालय के पत्र संख्या 3951/39याता-7/2024 दिनांक 15.10.2024 द्वारा स्वीकृत। -- as on 26-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: