Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
39W992 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी रूद्रप्रयाग का पत्र संख्या 163/जि0यो0-3/2023-24 दिनांक 05.06.2023
TS Amount (lakhs) : 12 Lacs
Financial Detail
Sanction Cost : 12.00 Lacs
Resanction Cost : 12.00 Lacs
Exp. Upto Last Fy : 6.00 Lacs
For CFY 2024-2025
Remaining : 6.00 Lacs
Demand : 6.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 6.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
11 months 2 weeks ago
05 Jun 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 31-Dec-2023
Physical Peramenters