Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
39W999 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 उत्तराखण्ड, देहरादून का पत्र संख्या 895/07याता-पीएमजीएसवाई -नि0-।।। दिनांक 16.05.2023
TS Amount (lakhs) : 73.74 Lacs
Financial Detail
Sanction Cost : 73.74 Lacs
Resanction Cost : 73.74 Lacs
Exp. Upto Last Fy : 58.46 Lacs
For CFY 2024-2025
Remaining : 15.28 Lacs
Demand : 15.28 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 58.46 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5.00 किमी0 में पीसी का कार्य पूर्ण। नाली आदि का कार्य प्रगति में। -- as on 13-Dec-2023
Physical Peramenters