Work Profile Report [3W174]

fभfकयासैण बासोट घट्टी मोटर मार्ग के fकमी. 4 में बम्योली तक मोटर मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा.सं. 5578(।)/।।।(2)/10-50(प्रा.आ.)/09

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

50.40

Resanction Cost :

50.40

Tentative Cost :

50.40

Exp. Upto Last Fy :

0.40

For CFY 2024-2025

Remaining :

50.00

Demand :

5.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.40

Work deferred

Sanction on : 14 years 1 month ago

20 Oct 2010

Physical Progress:

At start of FY 2024-2025 :

10 %

Up to Date :

10 %

Tentative Completion date on : 2 years 4 months from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
4
-

Remark

view all

उक्त मोटर मार्ग के समरेखण में जिस भाग में वनभूमि प्रभावित हो रही थी उसमें पी0एम0जी0एस0वाई0 खण्ड द्वाराहाट द्वारा मोटर मार्ग का निर्माण कर दिया गया है। अतः इस मार्ग का वनभूमि हस्तान्तरण प्रस्ताव निरस्त किया जाना है। अवशेष मार्ग की लम्बाई जो नापभूमि में से होकर जा रही है उस भाग का आगणन गठित कर मुख्य अभियन्ता, लो0नि0वि0, अल्मोड़ा के पत्रांक 748/101याता-अ/2022 दिनांक 09.02.2023 द्वारा उत्तराखण्ड शासन देहरादून को प्रेषित। -- as on 06-Nov-2024

Rating : 14

Forest Case Pending At : 01: Withdraw

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand