Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8 | 0 |
3W175 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 6229(1)/।।।(2)/10-19(प्रा.आ.) /09 दि. 15.10.10
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 100.80 Lacs
Resanction Cost : 100.80 Lacs
Exp. Upto Last Fy : 7.02 Lacs
For CFY 2024-2025
Remaining : 93.78 Lacs
Demand : 25.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 7.02 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
13 years 7 months ago
15 Oct 2010
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
नाप भूमि प्रस्ताव गठित। सत्यापन किया जा रहा है। -- as on 08-Apr-2024
Physical Peramenters