Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.5 | 0 |
3W212 :
Work not linked with IM
Bridges on The Basis of AI: Kafda Bridge
Administrative Approval Detail : शा.सं. 1440/।।।(2)/।।-05(प्रा.आ.)/2010 दि. 28.03.11
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
31.50
Resanction Cost :
31.50
Tentative Cost :
31.50
Exp. Upto Last Fy : 2.31
For CFY 2024-2025
Remaining : 29.19
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.31
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
13 years 3 months ago
28 Mar 2011
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
मुआवजा प्रस्ताव गठित। सत्यापन किया जा रहा है। -- as on 08-Apr-2024
Physical Peramenters