Work Profile Report [3W214]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. 1440/।।।(2)/।।-05(प्रा.आ.)/2010 दि. 28.03.11
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
100.80
Resanction Cost :
100.80
Tentative Cost :
100.80
Exp. Upto Last Fy :
8.07
For CFY 2024-2025
Remaining :
92.73
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
8.07
Construction Started
Sanction on : 13 years 8 months ago
28 Mar 2011
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
90 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date : 13 years 8 months ago
01 Apr 2011
Physical Linear Components
Remark
उत्तराखण्ड शासन देहरादून के पत्रांक 695/एक्स-4/16-1(599)/2015 दिनांक 13.12.2016 द्वारा विधिवत स्वीकृति प्राप्त। मार्ग निर्माण हेतु द्वितीय चरण की स्वीकृति प्राप्त। -- as on 01-Nov-2021
Assets :
Work not linked with IM
Bridges on The Basis of AI: