Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 0.000 | 6 | 0.000 | 0.000 |
Span of Bridges [m] | 36 | 36 | 0.000 | 36 | 0.000 | 0.000 |
3W237 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.स. 4997/।।र्।)।।-31(प्रा.आ.)/2011 दि. 19 सितम्बर, 2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
78.12
Resanction Cost :
78.12
Tentative Cost :
78.12
Exp. Upto Last Fy : 7.01
For CFY 2024-2025
Remaining : 71.11
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 7.01
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
12 years 9 months ago
19 Sep 2011
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मुआवजा प्रस्ताव गठित किया जाना है। -- as on 04-Feb-2023
Physical Peramenters