Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 72 | 72 | 72 | 0 |
Closed Work 3W242 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Pedestrain Bridge at Deghat
Administrative Approval Detail : शा.स. 6685/।।।(2)/11-65(प्रा.आ.)/07 दि. 24.12.2011
TS Amount (lakhs) : 341.63 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
341.63
Resanction Cost :
341.63
Tentative Cost :
341.63
Exp. Upto Last Fy : 341.62
For CFY 2024-2025
Remaining : 0.01
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 341.62
Work completed
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 100 %
Sanction on :
12 years 6 months ago
24 Dec 2011
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सेतु का निर्माण पूर्ण। -- as on 11-Apr-2022