Work Profile Report [3W242]
Fin Plan
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.स. 6685/।।।(2)/11-65(प्रा.आ.)/07 दि. 24.12.2011
TS Amount (lakhs) : 341.63 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
341.63
Resanction Cost :
341.63
Tentative Cost :
341.63
Exp. Upto Last Fy :
341.62
For CFY 2024-2025
Remaining :
0.01
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
341.62
Work completed
Sanction on : 13 years 3 days ago
24 Dec 2011
Physical Progress:
At start of FY 2024-2025 :
76 %
Up to Date :
100 %
Tentative Completion date on : 2 years 8 months ago
31 Mar 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सेतु का निर्माण पूर्ण। -- as on 11-Apr-2022
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: Pedestrain Bridge at Deghat
© PWD Uttarakhand