Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15 | 10.72 | 10.72 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 20 | 20 | 20 | 0 |
3W271 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Pedestrain Bridge at Deghat
Administrative Approval Detail : 289/।।।(2)/08-47(प्रा.आ.)/07 दिनांक 20.03.2008
TS Amount (lakhs) : 579.69 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
579.69
Resanction Cost :
579.69
Tentative Cost :
579.69
Exp. Upto Last Fy : 565.16
For CFY 2024-2025
Remaining : 14.53
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 565.16
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
16 years 3 months ago
20 Mar 2008
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
भौतिक रूप से कार्य मार्च 2022 में पूर्ण। कार्य में बचत की धनराशि रू0 14.53 लाख मात्र समर्पित की जानी है। -- as on 04-Jul-2024