Work Profile Report [3W272]
Fin Plan
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : अर्थ एवं संख्याधिकारी, अल्मोड़ा का पत्रांक 1580/जि0यो0(स्वी0)/13-14 दि. 04.10.13
TS Amount (lakhs) : 8 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8.00
Resanction Cost :
8.00
Tentative Cost :
8.00
Exp. Upto Last Fy :
8.00
For CFY 2024-2025
Remaining :
0.00
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
8.00
Work completed
Sanction on : 11 years 2 months ago
04 Oct 2013
Physical Progress:
At start of FY 2024-2025 :
77 %
Up to Date :
0 %
Tentative Completion date on : 7 years 8 months ago
31 Mar 2017
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
माह 01/2015 में 1 जाॅब कार्य पूर्ण।
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Pedestrain Bridge at Deghat