Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
3W339 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4417/।।।(2)/15-04(मु0मं0घो0)/2015 दिनांक 27.05.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
18.13
Resanction Cost :
18.13
Tentative Cost :
18.13
Exp. Upto Last Fy : 0.20
For CFY 2024-2025
Remaining : 17.93
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
9 years 1 month ago
27 May 2015
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
सैद्धान्तिक स्वीकृति की शर्तों मंे उल्लिखित शर्तो की अनुपालन आख्या इस कार्यालय के पत्रांक 1846/36सी. दिनांक 01.09.2022 को प्रभागीय वनाधिकारी, अल्मोड़ा को प्रेषित तथा पोर्टल पर आनलाईन प्रेषित। -- as on 27-Apr-2024
Physical Peramenters