Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.6 | 2.6 | 2.6 | 0 |
3W402 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1549/।।।(2)/17-49(एम0एल0ए0)/2017 दिनांक 28.07.2017
TS Amount (lakhs) : 51.57 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
51.57
Resanction Cost :
51.57
Tentative Cost :
51.57
Exp. Upto Last Fy : 41.07
For CFY 2024-2025
Remaining : 10.50
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 41.07
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 11 months ago
28 Jul 2017
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
5 years 2 months ago
01 May 2019
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 31-Jul-2020
Physical Peramenters