Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15 | 15 | 15 | 0 |
3W41 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 59लो0नि0-2/04-41(प्रा0आ0)/03 दि0 22.1.04
TS Amount (lakhs) : 62.8 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
62.80
Resanction Cost :
62.80
Tentative Cost :
62.80
Exp. Upto Last Fy : 41.57
For CFY 2024-2025
Remaining : 21.23
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 41.57
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
20 years 5 months ago
22 Jan 2004
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मुआवजा प्रस्ताव गठित। राजस्व विभाग से सत्यापन कराया जा रहा है। -- as on 03-Jun-2022
Physical Peramenters