Work Profile

3W41 :

No Pic Avilable Time series Gantt
सौनी ड्योड़ाखाल सिलोर महादेव मोटर मार्ग। (किमी. 21 से 35)


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 59लो0नि0-2/04-41(प्रा0आ0)/03 दि0 22.1.04

TS Amount (lakhs) : 62.8 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

62.80

Resanction Cost :

62.80

Tentative Cost :

62.80

Exp. Upto Last Fy : 41.57

For CFY 2024-2025

Remaining : 21.23

Demand : 20.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 41.57

Construction Started

Physical Progress:

At start of FY 2024-2025 : 80 %

Up to Date : 80 %

Sanction on :
20 years 5 months ago
22 Jan 2004


Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024


Actual Completion Date:
Not Yet Reported


Rating : 80

Remark

Bottelneck: no issue


मुआवजा प्रस्ताव गठित। राजस्व विभाग से सत्यापन कराया जा रहा है। -- as on 03-Jun-2022

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 15 15 15 0
Currently only Bank Gaurantee information is avilable