Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.85 | 0.85 | 0.850 | 0 | 0.000 | 0.000 |
3W422 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 44/।।।(2)/18-49(एम0एल0ए0)/2017 दि0 08.01.2018
TS Amount (lakhs) : 56.22 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
56.22
Resanction Cost :
56.22
Tentative Cost :
56.22
Exp. Upto Last Fy : 17.98
For CFY 2024-2025
Remaining : 38.24
Demand : 20.00
Allotment : 6.00
Exp in CFY : 5.97
Total Up to Date Exp : 23.95
Work completed
Physical Progress:
At start of FY 2024-2025 : 77 %
Up to Date : 100 %
Sanction on :
6 years 6 months ago
08 Jan 2018
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 31-Mar-2021
Physical Peramenters