Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.85 | 0.85 | 0.85 | 0 |
3W422 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 44/।।।(2)/18-49(एम0एल0ए0)/2017 दि0 08.01.2018
TS Amount (lakhs) : 56.22 Lacs
Financial Detail
Sanction Cost : 56.22 Lacs
Resanction Cost : 56.22 Lacs
Exp. Upto Last Fy : 17.98 Lacs
For CFY 2024-2025
Remaining : 38.24 Lacs
Demand : 20.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 17.98 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 77 %
Up to Date : 77 %
Sanction on :
6 years 4 months ago
08 Jan 2018
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 31-Mar-2021
Physical Peramenters