Work Profile Report [3W422]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : 44/।।।(2)/18-49(एम0एल0ए0)/2017 दि0 08.01.2018
TS Amount (lakhs) : 56.22 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
56.22
Resanction Cost :
56.22
Tentative Cost :
42.98
Saving
13.24
Exp. Upto Last Fy :
17.98
For CFY 2024-2025
Remaining :
38.24
Demand :
25.00
Allotment :
20.00
Exp in CFY :
13.75
Total Up to Date Exp :
31.73
Construction Started
Sanction on : 6 years 11 months ago
08 Jan 2018
Physical Progress:
At start of FY 2024-2025 :
77 %
Up to Date :
65 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 13.24 has been recorded as expected cost of work reduced from 56.22 to 42.98 . -- as on 03-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand