Work Profile Report [3W446]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : 4258/।।।(2)/18-05(प्रा0आ0)/2010 टी0सी0 दिनांक 21.08.2018
TS Amount (lakhs) : 234.94 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
291.75
Resanction Cost :
291.75
Tentative Cost :
268.09
Saving
23.66
Exp. Upto Last Fy :
243.09
For CFY 2024-2025
Remaining :
48.66
Demand :
25.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
243.09
Work completed
Sanction on : 6 years 3 months ago
21 Aug 2018
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 7 months ago
31 Mar 2023
Actual Completion Date : 1 year 9 months ago
01 Feb 2023
Physical Linear Components
Remark
Overall Saving 23.66 has been recorded as expected cost of work reduced from 291.75 to 268.09 . -- as on 20-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand