Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.15 | 4.15 | 4.15 | 0 |
3W446 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4258/।।।(2)/18-05(प्रा0आ0)/2010 टी0सी0 दिनांक 21.08.2018
TS Amount (lakhs) : 234.94 Lacs
Financial Detail
Sanction Cost : 291.75 Lacs
Resanction Cost : 291.75 Lacs
Exp. Upto Last Fy : 243.09 Lacs
For CFY 2024-2025
Remaining : 48.66 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 243.09 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 8 months ago
21 Aug 2018
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 04-Feb-2023
Physical Peramenters