Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 6 | 6 | 6 | 0 |
3W465 :
Administrative Approval Detail : 684/।।।(2)/19-51(एम0एल0ए0)/2017 टी0सी0 दि0 15.02.2019
TS Amount (lakhs) : 281.12 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
281.12
Resanction Cost :
281.12
Tentative Cost :
281.12
Exp. Upto Last Fy : 248.76
For CFY 2024-2025
Remaining : 32.36
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 248.76
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
5 years 5 months ago
15 Feb 2019
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
4.00 किमी0 लम्बाई में पहाड़ कटान एवं 4.00 किमी0 लम्बाई में पार्ट-।। का कार्य पूर्ण। अवशेष भाग में सैन्य विवाद होने के कारण आंशिक चैाड़ाई में मार्ग निर्माण पूर्ण। -- as on 08-Apr-2024
Physical Peramenters