Work Profile Report [3W475]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : 653/।।।(2)/19-24(प्रा0आ0)/2008 दि0 12.02.2019
TS Amount (lakhs) : 604.18 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
604.18
Resanction Cost :
604.18
Tentative Cost :
476.98
Saving
127.20
Exp. Upto Last Fy :
456.98
For CFY 2024-2025
Remaining :
147.20
Demand :
20.00
Allotment :
50.00
Exp in CFY :
28.83
Total Up to Date Exp :
485.81
Work completed
Sanction on : 5 years 9 months ago
12 Feb 2019
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 7 months ago
31 Mar 2022
Actual Completion Date : 2 years 8 months ago
03 Mar 2022
Physical Linear Components
Remark
Overall Saving 127.2 has been recorded as expected cost of work reduced from 604.18 to 476.98 . -- as on 23-Jul-2024