Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.05 | 6.05 | 6.05 | 0 |
3W498 :
Administrative Approval Detail : 3381/।।।(2)/19-50(एम0एल0ए0)/2017 दिनांक 06.09.2019
TS Amount (lakhs) : 304.09 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
304.09
Resanction Cost :
304.09
Tentative Cost :
304.09
Exp. Upto Last Fy : 235.46
For CFY 2024-2025
Remaining : 68.63
Demand : 30.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 235.46
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 10 months ago
06 Sep 2019
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 10-Mar-2023
Physical Peramenters