Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 4 | 4 | 0 |
3W5 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2454/111-2/05-07(प्रा0आ0)/05 टी.सी.-1 दि. 28.10.05
TS Amount (lakhs) : 140.53 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
166.80
Resanction Cost :
166.80
Tentative Cost :
166.80
Exp. Upto Last Fy : 146.41
For CFY 2024-2025
Remaining : 20.39
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 146.41
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
18 years 8 months ago
28 Oct 2005
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
मुआवजा प्रस्ताव गठित। सत्यापन उपरान्त भुगतान किया जायेगा। -- as on 10-Apr-2024
Physical Peramenters