Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 |
3W52 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 288लो0नि0-2/04-15(प्रा0आ0)/04 दि. 27.02.04
TS Amount (lakhs) : 83.4 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
83.40
Resanction Cost :
83.40
Tentative Cost :
83.40
Exp. Upto Last Fy : 54.54
For CFY 2024-2025
Remaining : 28.86
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 54.54
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
20 years 4 months ago
27 Feb 2004
Tentative Completion date:
1 year 8 months from now
31 Mar 2026
Actual Completion Date:
3 years 3 months ago
01 Apr 2021
Remark
Forest Status 21: Final
Bottelneck: no issue
पुन एस्टीमेट क्षेत्रीय कार्यालय अल्मोड़ा से आपत्तियां में प्राप्त आपत्तियों का निराकरण प्रेषित कर दिया जाएगा -- as on 13-Jul-2024
Physical Peramenters