Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
3W520 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 2243/।।।(2)/20-50(एम0एल0ए0)/2017टी0सी01 दिनांक 16.12.2.2020
TS Amount (lakhs) : 240.76 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
240.76
Resanction Cost :
240.76
Tentative Cost :
240.76
Exp. Upto Last Fy : 215.69
For CFY 2024-2025
Remaining : 25.07
Demand : 5.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 215.69
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 7 months ago
16 Dec 2020
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। पंचवर्षीय अनुरक्षण का कार्य गतिमान। -- as on 03-Jul-2024
Physical Peramenters