Administrative Approval Detail : 321/।।।(2)/21-49(एम0एल0ए0)/2017टीसी।। दि0 24.02.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
57.71
Resanction Cost :
57.71
Tentative Cost :
43.03
Saving
14.68
Exp. Upto Last Fy :
18.03
For CFY 2024-2025
Remaining :
39.68
Demand :
25.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
18.03
Work completed
Sanction on : 3 years 10 months ago
24 Feb 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 3 weeks ago
30 Nov 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 14.68 has been recorded as expected cost of work reduced from 57.71 to 43.03 .
कार्य पूर्ण। दायित्वों का भुगतान शेष।
-- as on 20-Jul-2024