Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.92 | 1.92 | 1.92 | 0 |
3W539 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 321/।।।(2)/21-49(एम0एल0ए0)/2017टीसी।। दि0 24.02.2021
TS Amount (lakhs) : 6351000 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
63.51
Resanction Cost :
63.51
Tentative Cost :
63.51
Exp. Upto Last Fy : 38.90
For CFY 2024-2025
Remaining : 24.61
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 38.90
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 4 months ago
24 Feb 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
2 years 2 weeks ago
30 Jun 2022
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्वों का भुगतान शेष। -- as on 07-Jul-2022
Physical Peramenters