Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 22 | 22 | 0.000 | 22 | 0.000 | 0.000 |
3W562 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2630/III(2)/21-49(MLA)/2017 T.C. I
TS Amount (lakhs) : 10.07 Lacs
Financial Detail
Sanction Cost : 122.32 Lacs
Resanction Cost : 122.32 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 122.32 Lacs
Demand : 0.20 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 9 months ago
11 Aug 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
भू निरीक्षण हेतु भू-वैज्ञानिक को पत्र प्रेषित। -- as on 04-Aug-2023
Physical Peramenters