Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.625 | 3.625 | 3.625 | 0 |
3W572 :
Administrative Approval Detail : 4800/III(2)/21-51(MLA)/2015
TS Amount (lakhs) : 229.16 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
229.16
Resanction Cost :
229.16
Tentative Cost :
229.16
Exp. Upto Last Fy : 226.09
For CFY 2024-2025
Remaining : 3.07
Demand : 3.07
Allotment : 3.00
Exp in CFY : 0.00
Total Up to Date Exp : 226.09
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 9 months ago
06 Oct 2021
Tentative Completion date:
1 year 2 weeks ago
30 Jun 2023
Actual Completion Date:
1 year 2 months ago
09 May 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। मार्ग डी0एल0पी0 के अन्तर्गत है। -- as on 08-Apr-2024
Physical Peramenters