Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.825 | 2.825 | 2.825 | 0 |
3W619 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File No 34908 dated 21-10-2022
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 50.17 Lacs
Resanction Cost : 50.17 Lacs
Exp. Upto Last Fy : 22.03 Lacs
For CFY 2024-2025
Remaining : 28.14 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 22.03 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
1 year 6 months ago
21 Oct 2022
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 05-Oct-2023
Physical Peramenters