Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 24.49 | 27.49 | 27.49 | 0 |
3W653 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 895/07Yata-PMGSY-Ni III dated 16-05-2023
TS Amount (lakhs) : 420.25 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
420.25
Resanction Cost :
420.25
Tentative Cost :
420.25
Exp. Upto Last Fy : 303.53
For CFY 2024-2025
Remaining : 116.72
Demand : 60.00
Allotment : 60.00
Exp in CFY : 0.00
Total Up to Date Exp : 303.53
Work completed
Physical Progress:
At start of FY 2024-2025 : 99 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 07-Jun-2024
Physical Peramenters