Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.1 | 6.1 | 6.1 | 0 |
3W657 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 895/07Yata-PMGSY-Ni III dated 16-05-2023
TS Amount (lakhs) : 57.61 Lacs
Financial Detail
Sanction Cost : 57.61 Lacs
Resanction Cost : 57.61 Lacs
Exp. Upto Last Fy : 42.58 Lacs
For CFY 2024-2025
Remaining : 15.03 Lacs
Demand : 15.03 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 42.58 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 01-Nov-2023
Physical Peramenters