Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
3W671 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 403/(लोक निर्माण विभाग)/जि0यो0/2023-24
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
10.00
Resanction Cost :
10.00
Tentative Cost :
10.00
Exp. Upto Last Fy : 2.12
For CFY 2024-2025
Remaining : 7.88
Demand : 7.88
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.12
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
1 year 3 weeks ago
21 Jun 2023
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 09-Apr-2024
Physical Peramenters