Work Profile

अमेता से पातल के रौले तक सम्पर्क मार्ग का निर्माण।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 403/(लोक निर्माण विभाग)/जि0यो0/2023-24

TS Amount (lakhs) : 0 Lacs

Financial Detail

Sanction Cost : 5.00 Lacs

Resanction Cost : 5.00 Lacs

Exp. Upto Last Fy : 3.77 Lacs

For CFY 2024-2025

Remaining : 1.23 Lacs

Demand : 1.23 Lacs

Allotment : 0.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 3.77 Lacs

Work completed

Physical Progress:

At start of FY 2024-2025 : 100 %

Up to Date : 100 %

Sanction on :
10 months 4 weeks ago
21 Jun 2023


Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024


Actual Completion Date:
Not Yet Reported


Rating : 100

Remark

Bottelneck: no issue


कार्य पूर्ण। दायित्व शेष। -- as on 09-Apr-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Jobs 1 1 1 0
Currently only Bank Gaurantee information is avilable