Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 22 | 22 | 0.000 | 22 | 5.000 | 0.000 |
3W7 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2751/111-2/06-49(प्रा0आ0)/06 दि. 22.11.06
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 469.72 Lacs
Resanction Cost : 469.72 Lacs
Exp. Upto Last Fy : 58.58 Lacs
For CFY 2024-2025
Remaining : 411.14 Lacs
Demand : 80.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 58.58 Lacs
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
17 years 5 months ago
22 Nov 2006
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
खण्डीय कार्यालय के पत्रांक 555/36सी. दिनांक 28.02.2024 द्वारा अनुपालन आख्या प्रेषित। प्रभागीय वनाधिकारी, अल्मोड़ा के पत्रांक 4073/12-1(2) दिनांक 29.02.2023 द्वारा मार्ग निर्माण मंे कार्य प्रारम्भ करने हेतु अनुमति प्राप्त। लाॅट संख्या 46 के पातन हेतु वन विकास निगम को धनराशि का भुगतान माह 03/2024 मंे कर दिया गया है। -- as on 27-Apr-2024
Physical Peramenters