Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 22 | 22 | 0.000 | 22 | 5.000 | 0.000 |
3W7 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2751/111-2/06-49(प्रा0आ0)/06 दि. 22.11.06
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
469.72
Resanction Cost :
469.72
Tentative Cost :
469.72
Exp. Upto Last Fy : 58.58
For CFY 2024-2025
Remaining : 411.14
Demand : 80.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 58.58
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 60 %
Sanction on :
17 years 7 months ago
22 Nov 2006
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
5.00 किमी0 में पहाड़ कटान एवं 2.00 किमी0 में पार्ट-।। का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 12-Jul-2024
Physical Peramenters