Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.7 | 4.7 | 0.000 | 4.7 | 4.700 | 0.000 |
3W701 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No 48456
TS Amount (lakhs) : 81.79 Lacs
Financial Detail
Sanction Cost : 81.79 Lacs
Resanction Cost : 81.79 Lacs
Exp. Upto Last Fy : 6.68 Lacs
For CFY 2024-2025
Remaining : 75.11 Lacs
Demand : 60.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 6.68 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
9 months 1 week ago
10 Aug 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित कर स्कपर निर्माण का कार्य प्रगति पर। -- as on 14-Dec-2023
Physical Peramenters